Linac Modulator Testing - Fermilab

Linac Modulator Testing Fermilab-ppt Download

  • Date:29 Sep 2020
  • Views:34
  • Downloads:0
  • Size:3.87 MB

Share Presentation : Linac Modulator Testing Fermilab

Download and Preview : Linac Modulator Testing Fermilab

Report CopyRight/DMCA Form For : Linac Modulator Testing Fermilab


Transcription:

Linac Marx Modulator UpdateMatt Gardner Trevor ButlerPIP General Meeting23 March 2016 54 Cell Prototype.
Marx Cabinet Cells Internal assembly of cell support structure completed Output circuits hardware still need to be installed Cells are being assembled Capacitor assembly and frame heat sync assemblies are complete for all cells The two.
assemblies are being put together Charging Supplies All 24 supplies have been delivered with 17 tested so far without any failures Charging supply cabinet was delivered All internal wiring needs to be designed and installed.
Summing plate still needs to be designed and built Controls Controls crate has been assembled with all cards except the FPGA control board FPGA control board is still being designed Crate needs to be wired a few days worth of work .
Crate needs a power supply The 28 cell prototype controls crate borrowed a supply from the EE Support kicker group which is highly over spec d for this use A new supply must either be built or purchased2 Presenter Presentation Title 09 29 2020.
54 Cell Prototype Cabinet3 Presenter Presentation Title 09 29 2020 New Cabinet for Capacitor Charging Power Supplies4 Trevor Butler Linac Modulator Testing 09 29 2020 LRF1 Marx Modulator Testing all 4 cavity regulation schemes.
Digital Feedforward Open Loop Implement R L or Proportional and Differential response assuming a specific gain of the 7835 R Proportional and responseof the cavity L or Differential Looking into the best way to make changes to these parameters after a tube change out occurs without calling in experts Digital Learning Pulse to Pulse .
The pulse to pulse wave shaping the is used to flatten the cavity fields Will shape the rising edge of the waveform and slope of the PWM to keep the cavity fields flat Will not account for pulse to pulse changes which can be as large at a few percent on LRF1 without addition control Analog Feed Forward Closed Loop Voltage minus Current is proportional to cavity gradient error.
Set gain to minimize the cavity pulse to pulse error Activates on flattop and held right before beam enters cavity since this effects the response of the tube Plan to convert this to a Howie defined JITR algorithm Just In Time Regulation which will use the cavity gradient errorsampled early in the pulse to ramp up the PWM values to compensate for pulse to pulse variations 54 cell design Analog Feed Back Closed Loop .
Compares actual cavity to desired cavity signal after going through lead out network Works along side Analog Feed Forward to flatten cavity fields Also activated on entire flattop Digital Beam Control Feedforward and Learning Presently used the LLRF Feed Forward command to switch in Beam Pulse from Marx Controls.
Turns on special cell to learned voltage Adds additional signal to PWM to learn wave shaping required to flatten the gradient Ideadlly we could use beam start time and width information to replace the present5 Trevor Butler Linac Modulator Testing 09 29 2020 LRF1 Marx Modulator Progress since last report.
Goal since last meeting Get the Marx Modulator system operational for long term testing Resolved Driver Low Problem We think it is the fact that the modulator was not shutting offafter a cavity spark causing instabilities in the 7835 output power which feedback into thedriver power level Resolved problem when going from short to long pulses where the learning would not.
update correctly Installed new Ross Voltage Divider and interfaced with Marx Controls Installed HV Ross Relay on output of modulator before the RG220 Output cable Unless we can assure limit of 1000 mrem hr of xrays that could be emitted from the cavity we needto implement a two independent methods of turning limiting power out of the modulator.
Worked with safety to implement a tunnel access interlock that both grounds out the HV capacitorcharging supplies and the output of the Marx modulator when activated Wired in HV On which is used to turn on the Driver Anode HV power supply in order to tripoff Marx modulator when Driver or other subsystem trip off Installed new Humidity Sensors on 7835 and 4616 Cavities.
Testing Interlocks between Marx and Linac control system Added wiring for Driver Start Pulse Driver Stop Pulse LLRF Gating Pulse to providesignals required to operate the drive without the A5 controls 6 Trevor Butler Linac Modulator Testing 09 29 2020 LRF1 Marx Modulator Latest Results.
Ch 1 LLRF Beam FF Signal Ch 1 Modulator Voltage 5kV V Ch 2 Modulator Voltage 5kV V Ch 2 Feed forward error Ch 3 Gradient error Ch 3 Gradient error Ch 4 Unused Ch 4 Beam timing pulse7 Trevor Butler Linac Modulator Testing 09 29 2020.
LRF1 Marx Modulator Pulse to Pulse Stability Decreased the standard deviation of pulse to pulse variations from 16 to about 0 04 We also measured an overall gradient variation using an oscilloscope of around 1 on tubemodulator and about 0 25 on Marx modulator 8 Trevor Butler Linac Modulator Testing 09 29 2020.
LRF1 Marx Modulator Next Steps to Full OperationSteps remaining to finalize switchover on LRF1 Run for the next two weeks with the present system to look for any failure modes that mayoccur in the modulator Ideally resolve any issues without switching back Build analog reference circuit into analog comparator board that could be used to regulate.
the capacitor charging supply voltage Update code to reflect changes in beam learning during turnoff advance Document present setting on both waveform and system timing Finalize switch over to driver On Off controls to enable replacement of present Modulatorcontrol system which is being partially hijacked to enable operation of the Marx using its.
interlock and driver level commands Work on building spare parts control cards power supplies etc to enable us to have ansystem can could run in this mode and be able to repair parts instead of switching right back Need to determine best way to remove requirements of keeping the old modulator parts such as Crowbar Cabinets power up to make up the required interlocks.
Will need new LOTO procedure written and new interlock configuration explained Continued training of Linac and Operational personnel of system functionality 9 Trevor Butler Linac Modulator Testing 09 29 2020 End Start of running10 Trevor Butler Linac Modulator Testing 09 29 2020.
Output circuits / hardware still need to be installed. ... which is used to turn on the Driver Anode HV power supply, in order to trip off Marx modulator when Driver or other subsystem trip off. ... Testing Interlocks between Marx and Linac control system. Added wiring for Driver Start Pulse, Driver Stop Pulse, & LLRF Gating Pulse to provide ...

Related Presentations

Linac PIP Modulator Update Fermilab

Additional electrical tech to aid in assembly. Marx Modulator Cabinet for Cells. Short Circuit Problems. Gate Driver Circuit Board . Controls the firing of the main IGBT to create the modulator waveform. 25 Gate Drive Boards have already been built.

13 Views0 Downloads

Unit Testing System Testing HCI Usability Testing

Testing HCI Usability Testing ... all events that cause a state change in the object Integration testing is replaced by thread-based testing -- test the set of classes required to respond to an input or system event or use case scenario. HCI Usability Testing Users give satisfaction ratings and critiques regarding interaction with the system ...

37 Views0 Downloads

Testing Testing Testing msdnshared blob core windows net

Agenda. Introducción a las pruebas. Tipos de Pruebas. Pruebas Unitarias. Pruebas de Integración. Pruebas Funcionales. Pruebas de Rendimiento. Integración con TeamFoundation

28 Views0 Downloads

WAO 2012 Summary www linac kek jp

WAO 2012 Summary. WAO 2012 Summary . Sleep Research - physiological responses - sleep disorders - simple measures (light exposure, sleeping environment) - Slides of the talk will be posted on the WAO website - Further Questions for Dr. Kushida can be emailed to [email protected]

19 Views0 Downloads

WAO 2012 www linac kek jp

Welcome to WAO 2012. Lunches – 1 hour. Pre-paid – tickets inside name tag. WAO 2012 Tables outside Research Office Building (behind Kavli) Not pre-paid – SLAC Cafeteria, Off-site options. Opportunity to meet and interact with other WAO participants. Tuesday Banquet 18:30. Quadrus Conference Center (across Sand Hill Rd)

17 Views0 Downloads

Linac 400 MeV BPM System Plans and Status Nathan Eddy PIP

Compute position averages and deliver all of the position data to the ACNET control system every 66 ms (15HZ) A limited number of BPM’s in the Linac and 400 MeV line will be required to deliver all of the position data samples to applications running in ACNET at the 15 Hz rate

12 Views0 Downloads

Linac and BunCh Compression Stanford University

of passive de-chirping insertion on machine . design. Lowering degree of RF (velocity bunching) compression. Requirements informing choice of linacdesign. All bunches exiting the linachave same design characteristics, are adequate to feed any of the FEL beamlines (1keV photon /energy)

11 Views0 Downloads

Project X Beam Instrumentation in the High Energy Linac

11/22/2008 Summary: Project X Instrumentation WG * Definition of Collaborations Needs a very clear plan: Exact definition of the R&D project Detailed instrumentation specs Scope and deliverables (can be anything between consulting and a complete turn-key system) Schedule and milestones Hard- and software integration Realistic cost estimation (M ...

4 Views0 Downloads

High Current Energy Recovery Linac at BNL

Outline ERL prototype Goals & Parameters Step by Step tests SRF gun, SRF cavity, beam dump Future steps: return loop for ERL - single and double turns beam stability and feedbacks tests ERL modes of operation CW and test modes for Navy and DoE Test relevant for the eRHIC concept Conclusion Goals for ERL R&D program at BNL Test the key ...

4 Views0 Downloads

Inj group 150318 www linac kek jp

500 mJ for Ir. 5 Ce cathode 50 mJ for Ce. 2 Te cathode50 Hz, 2-bunch (96ns spacing) => Regenerative amplifier + 96ns delay => Large regenerative amplifier (unstable) => Multi-pass amplifier (Upgrade existing underground laser ) Temporal pulse shaping to reduce energy spread => Broadband laser crystal (Yb or Ti:Sapphire) => postponded until ...

3 Views0 Downloads

Coagulation Testing Point of care Testing

JCAHO Joint Commission on Accreditation of Health Care Orgs CAP College of American Pathologists FDA Food and Drug Administration CDRH Center for Devices and Radiological Health CMS Centers for Medicare and Medicaid Services CDC Centers for Disease Control CLIA Applies to ALL Testing Areas Central Laboratory Satellite Labs Critical Care ...

32 Views0 Downloads

Growing testing skills using the Agile Testing Ecosystem

Good way to communicate how testing can play a part throughout the whole sprint, not just using testing as a safety mechanism at the end. Years of advocacy on risk-based testing, exploratory testing, and embedding testers through agile development teams – but this model has already yielded the most obvious “a-ha” moments.

16 Views0 Downloads